METIS BSPL (Beta Version)
Register
|
Contact Us
|
Forgot Password
Metis Advantage
Clients
Energy Dashboard
EnerBase
News
Tender
Projects
EnerCore
EnerPrime
Consulting & Advisory
Research & Publications
Research
Publications
Masterclass & Events
MasterClass
Events
In-House Training
Knowledge Hub
White Paper
Energy Calculator
Expert Speak
Project Tenders
Consultancy services for preparation of RFP docume
Multiple packages for different power projects in
"Water Pre-Treatment Plant Package For Nabinagar S
Supply And Installation Of 5 NOS. X 100 KWP Stand
Electrostatic Precipitator' Package For Gadarwara
80 MVAR reactor for RHEP
RFQ auxiliary pressure reducing and desuperheating
Providing Consultancy Services For Setting Up MW S
Erection Commissioning Of 7 Nos Solar PV Power Pla
Request for Proposal for Setting up Solar Power pr
Project News
Metis: R&M for 6 units and LE for 2 units achieved
Metis: Power Ministry's note on R&M of Thermal Pow
JSPL to come up with 1320 MW thermal power plant a
Metis: MoPNG passes the buck to GAIL, ONGC for Raj
JP Morgan may pick up INR 800-crore stake in Bhask
Metis: Sai Krishnodaya Industries seeks MoEF clear
Metis: JKSPDC reworks its plan for the 930MW Kirth
Metis: Sai Krishnodaya Industries seeks MoEF clear
Metis: PSC calls for "practical approach" to harne
Metis: Allocation does not mean assurance of gas s
Power
Coal
Oil & Gas
Upstream
LNG Terminals
Refinery
Product Pipelines
Natural Gas Pipelines
Search
Keywords
Fuel Type
Commissionaring Year
State
Select States
Andhra Pradesh
Arunachal Pradesh
Assam
Bihar
Chhattisgarh
Delhi
Goa
Gujarat
Haryana
Himachal Pradesh
Jammu & Kashmir
Jharkhand
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Manipur
Meghalaya
Mizoram
Nagaland
Orissa
Punjab
Rajasthan
Sikkim
Tamil Nadu
Tripura
Uttaranchal
Uttar Pradesh
West Bengal
My Space
Name
Developer
Category
State
Implementation
Capacity (MW)
Land Acquisition
Financial Closure
Fuel Type
PPA
Commissioning Year
RRVUNL: 330 MW Dholpur Gas Power Station
Rajasthan Rajya Vidyut Utpadan Nigam Ltd. Jaipur
Thermal
Rajasthan
Commissioned
330
Completed
Achieved
Gas
Tied Up
2008
SKIL: 80 MW Gimliang HEP
Sai Krishnodaya Industries Private Limited
Hydro
Arunachal Pradesh
Planning
80
Yet to begin
Yet to be achieved
Water
Yet to be tied up
NA
TNEB: 2000 MW Sillahalla HEP
TNEB (Tamil Nadu Electricity Board)
Hydro
Tamil Nadu
Planning
2000
Yet to begin
Yet to be achieved
Water
Yet to be tied up
NA
OTPC: 726.6 MW Palatana Gas Based Power Plant
Oil and Natural Gas Corporation, Tripura Power Development & IL&FS Corporation
Thermal
Tripura
Commissioned
726.6
Partial
Achieved
Gas
Tied up
2013
NDPL: 108 MW Rithala CCPP
North Delhi Power Ltd. (NDPL)
Thermal
Delhi
Commissioned
108
Completed
Achieved
Gas
Tied up
2011
Nabinagar: 1980 MW at Aurangabad
Nabinagar Power Generating Co. Pvt. Ltd
Thermal
Bihar
Under Execution
1980
Partial
Yet to be achieved
Coal
Partial
2018
NHPC: Dibang Multipurpose HEP
NHPC
Hydro
Arunachal Pradesh
Planning
3000
Yet to begin
Yet to be achieved
Water
Yet to be tied up
2020
NHPC: 105 MW Loktak HEP
NHPC
Hydro
Manipur
Commissioned
105
Completed
Achieved
Water
Tied Up
1983
PSEB: 134 MW Anandpur Sahib HEP
Punjab State Electricity Board (PSEB)
Hydro
Punjab
Commissioned
134
Completed
Achieved
Water
Tied Up
1985
PSEB: 110 MW Shanan HEP
Punjab State Electricity Board (PSEB)
Hydro
Punjab
Commissioned
110
Completed
Achieved
Water
Tied Up
1982
PSEB: 600 MW Ranjit HEP
Punjab State Electricity Board (PSEB)
Hydro
Punjab
Commissioned
600
Available
Achieved
Water
Tied Up
2000
Mahagenco: 1960 MW Pophali HEP
MahaGenco
Hydro
Maharashtra
Commissioned
1960
Completed
Achieved
Water
Tied Up
2000
GSECL: 240 MW Kadana HEP
Gujarat State Electricity Corporation Ltd (GSECL)
Hydro
Gujarat
Commissioned
240
Available
Achieved
Water
Tied Up
1998
GSECL: 305 MW Ukai HEP
Gujarat State Electricity Corporation Ltd (GSECL)
Hydro
Gujarat
Commissioned
305
Available
Achieved
Water
Tied Up
1988
APGCL: 100 MW Karbi Langpi HEP
Assam Power Generation Corporation Ltd.
Hydro
Assam
Commissioned
100
Completed
Achieved
Water
Tied Up
2007
NEEPCO: 130 MW Ranganadi HEP Stage II
North Eastern Electric Power Corporation Limited (NEEPCO)
Hydro
Arunachal Pradesh
Under Execution
130
Completed
Yet to be achieved
Water
Yet to be tied up
2013
DVC: 80 MW Panchet HEP
Damodar Valley Corporation (DVC)
Hydro
Jharkhand
Commissioned
80
Completed
Achieved
Water
Tied Up
1991
DVC: 60 MW Maithon HEP
Damodar Valley Corporation
Hydro
West Bengal
Commissioned
60
Completed
Achieved
Water
Tied Up
1958
NEEPCO: 405 MW Ranganadi HEP
North Eastern Electric Power Corporation Limited (NEEPCO)
Hydro
Arunachal Pradesh
Commissioned
405
Completed
Achieved
Water
Tied Up
2002
Malana Power: 200 MW Bara Bangahal HEP
Malana Power
Hydro
Himachal Pradesh
Under Execution
200
Completed
Yet to be achieved
Water
Yet to be tied up
2014
JKSPDC: 280 MW UJH HEP
JKSPDC
Hydro
Jammu & Kashmir
Planning
280
Yet to begin
Yet to be achieved
Water
Yet to be tied up
2017
APPDCL: 1600 MW Krishnapatnam Thermal Power Station
JV Between Andhra Pradesh Power Generation Corporation Limited (APGENCO) and IL&FS.
Thermal
Andhra Pradesh
Under execution
1600
Yet to begin
Achieved
Coal
Yet to be tied up
2013
UJVNL: 90 MW Maneri Bhali Phase-I
UJVNL
Hydro
Uttarakhand
Commissioned
90
Completed
Achieved
Water
Tied Up
1984
CESC: 600 MW Chandrapur TPP
CESC
Thermal
Maharashtra
Under Execution
600
Partial
Achieved
Coal
Tied Up
2014
Monnet Ispat: 660 MW Angul TPP
Monnet Ispat and Energy
Thermal
Orissa
Planning
660
Yet to begin
Yet to be achieved
Coal
Yet to be tied up
NA
Vedanta Aluminium Limited: 1215 MW Jharsuguda CPP
Vedanta Aluminium Limited
Thermal
Orissa
Commissioned
1215
Completed
Achieved
Coal
Tied Up
2008
GMR Energy: 225 MW Talong Londa HEP
GMR Energy Ltd
Hydro
Arunachal Pradesh
Under Execution
225
Yet to begin
Yet to be achieved
Water
Partial
2016
APGENCO: 50 MW Nagarjuna Sagar HEP
APGENCO
Hydro
Andhra Pradesh
Commissioned
50
Completed
Achieved
Water
Tied Up
2010
APGENCO: 120 MW Pulichintala HEP
APGENCO
Hydro
Andhra Pradesh
Under Execution
120
Yet to begin
Yet to be achieved
Water
Tied Up
2015
NEEPCO: 85 MW Mawphu HEP
North Eastern Electric Power Corporation Limited (NEEPCO)
Hydro
Meghalaya
Under Execution
85
Yet to begin
Not yet Achieved
Water
Yet to be tied up
2016